Favourite Icon
 

The Ottawa Hospital’s new campus is being built on a 50-acre site bordered by Carling Avenue, Preston Street, and Prince of Wales Drive, near Dow’s Lake in Ottawa. It will be home to a new state-of-the-art hospital, an ambulatory care and research building, life sciences buildings, parking garage and an energy efficient central utility plant.

Latest news/updates

Nov. 19, 2024:

Construction update: work is currently underway on the intersection at Carling Avenue and Champagne Avenue, where there will be an entrance into the new campus. Most of the updates are planned to be completed before the new year. Some seasonal work will continue into the spring of 2025. 

Some work on the parking garage will require access to the Trillium Line LRT trench. Construction crews will endeavor to complete as much work as possible during regular hours. However, some City-approved overnight work will be required over the next few weeks. Crews will make every possible effort to limit noise overnight.

Planning and development

The Ottawa Hospital works closely with provincial, municipal, and federal governments on planning the new campus. The Ontario Ministry of Health approves each stage of development, and the master site plan was approved by the City of Ottawa and the National Capital Commission in 2021. As plans are finalized for each stage of work on the site, the site plan is refined through approvals processes and feedback to ensure that the new hospital will meet the needs of our community, surrounding region and everyone we serve. 

Since February 2024, The Ottawa Hospital, Infrastructure Ontario, The Ottawa Hospital Build Partners, and the Ontario Ministry of Health have been working through a Development Phase Agreement to collaboratively to finalize designs, costs and construction schedule for the main hospital. This work will continue through 2025.

A $59 million federal grant announced in May 2024 meant TOH could continue plans to build a world-class Biotherapeutics Manufacturing Centre (BMC) at the new campus. The new BMC will boost local and national capacity to develop and manufacture life-saving biotherapeutics, including vaccines, gene therapies and cell therapies. This investment was made through the federal government’s integrated Canada Biomedical Research Fund and Biosciences Research Infrastructure Fund. 

The Ottawa Hospital continues to collaborate with Hydro Ottawa on plans for an energy efficient Central Utility Plant on the site. 

Construction

Construction on the parking garage to support the new campus started in the spring of 2023. In summer 2024, the garage began taking shape with the installation of large precast concrete elements section by section. As of October 2024, the east side of the parking garage near Preston Street and Prince of Wales Drive was in place. Construction on the west side of the garage began in November 2024. The two will be connected as a single structure over the top of the Trillium Line of the LRT trench. 

Site preparation is ongoing in the area where the main hospital will be built. Civil works, including utilities, work on site roads and work to connect the site to city streets have begun, and are planned to be completed before construction begins on the main hospital building.  

Throughout the project, TOH is working closely with arborists to preserve as many trees as possible. Because some trees will have to be removed due to construction, a tree conservation plan was developed with input by arborists and in consultation with the City of Ottawa and the National Capital Commission, and with TOH’s master site plan approved by the City of Ottawa. 

The aerial video below (from July) shows progress on the parking garage and the location of where the main hospital will be built. 

The photo gallery below shows the progress made since early 2023 on the parking garage that will support the new hospital.  

PG1
An aerial view in winter of the snow-covered construction site where the parking garage for The Ottawa Hospital’s new campus will be built. There are a few pieces of construction equipment, some trailers and a tractor on the site.

Snow covers the site where the parking garage will be located. Excavation has yet to begin. (January 2023)

PG2
An aerial view in spring of the construction site where the parking garage for The Ottawa Hospital’s new campus will be built. Construction crews are excavating the ground with backhoes and other heavy equipment.

Crews begin excavating the site of the parking garage. (April 2023)

PG3
An aerial view in fall of the construction site where the parking garage for The Ottawa Hospital’s new campus is being built. A large tower crane is on site and parts of the concrete foundation have been poured at ground level.

With a tower crane now onsite, crews begin building the foundation of the parking garage. (October 2023)

PG4
An aerial view in early spring of the construction site for the parking garage at The Ottawa Hospital’s new campus. Three large tower cranes are on the site. Large concrete structures like stairwells, elevator shafts and an entrance ramp for vehicles are partially built, extending vertically up from the ground level.

Two more tower cranes are now onsite, and work has begun on footings and concrete structures like stairwells, elevator shafts and an entrance ramp. (March 2024)

PG5
An aerial view in summer of the partially constructed parking garage at The Ottawa Hospital’s new campus. A large yellow crane is on the site, and multiple levels on one half of the parking garage have been built. An unfinished roof covers the portion of the garage that is complete.

The east side of the parking garage begins to take shape as crews continue to install large precast concrete elements that make up the structure. (July 2024)

PG6
An aerial view in the fall of the partially constructed parking garage at The Ottawa Hospital’s new campus. One half of the parking garage is completed, it has multiple levels and is covered by a roof.

Crews prepare to begin work on the west side of the parking garage (November 2024)

PG7
An aerial view in winter of the partially constructed parking garage at The Ottawa Hospital’s new campus. One half of the parking garage is completed and covered by snow, the early stages of construction have begun on the other half.

The most recent aerial photo of the parking garage shows the west side of the parking garage starting to take shape (December 2024)

previous arrow
next arrow
PG1
PG2
PG3
PG4
PG5
PG6
PG7
previous arrow
next arrow

Project Milestones

October 2021: Master site plan approved

November 2022: RFP issued for main hospital​

Spring 2023: Start of parking garage construction​

Fall 2023: RFP closes for main hospital​

2024/2025: Construction of Central Utility Plant​

2024/2025: Construction begins on main hospital​ ​

2025/2026: Construction of parking garage complete ​

2028/2029: Construction of main hospital complete​